 |
APPENDIX 1
CASE STUDIES
|
|
 |
CASE STUDY 1
UNIVERSITY OF TECHNOLOGY HAYMARKET CAMPUS, ULTIMO
| Client | University of Technology, Sydney |
 |
| Architect | Philip Cox; Richardson, Taylor &
Partners Pty. Ltd. |
| Builder | Concrete Constructions (N.S.W.) Pty.
Ltd. |
| Bricklayer | Reno Pty. Ltd. |
| Brick Supplier | Statebrick Pty. Ltd:
(a) Brickworks Red
(b) Cream Wirecut
(c) Salmon Wirecut |
| Contract Value | $20,000,000 |
| Brickwork Subcontract Value | $1,400,000 |
| | |
University of Technology, Sydney
Architect: Cox, Richardson, Taylor and Partners
Photo: Tom Balfour |
The building is a 3 and 4 level reinforced concrete frame with a non-load bearing
cavity brick facade. External brickwork throughout is banded in cream and salmon
coloured 8 course bands with a variety of large circular openings at windows and
louvres. The building was constructed from 1981 to 1983.
Relevant isues:
- Project Size
The 17,000 m2 building required a huge order of 1.2 million bricks. This
created an opportunity for the contractor to place a single brick order. The
opportunity was taken and large quantities of bricks were stored at the
brickmaker's yard (Statebricks, Blacktown - now closed). Towards the end
of the job, however, additional bricks had to be ordered and produced
afresh due to losses by wastage and some underestimating in the initial order
resulting in some brick colour batch problems.
- Characateristic of Expansion ('e' Factor)
Fortunately, as both the cream and the salmon brick were obtained from the
same clay materials fired to different temperatures and levels of oxidation, the
'e' factors were nearly identical. This minimised the problem of differential
brick expansion along the band joint. Advice on brick growth data was
provided by the Melbourne office of the Clay Brick and Paver Institute. The
similar 'e' factors between face bricks and the relatively weak mortar mix
resulted in the decision to not have a slip-joint in horizontal bed courses
between two bands.
- Brick Size
The longer firing period of the salmon brick resulted in a brick some 4mm
shorter than the cream. The consequence on site was to target 9mm
perpends for cream bricks and 13mm perpends for salmon bricks. This was
further complicated by considerable variation in brick length within each
colour. The result, in parts, is some unsightly fat perpends and smaller areas
of excessively tight (i.e. 4mm) perpends to maintain horizontal gauge.
Coping successfully with the basic size and gauge differences between cream
and salmon bricks, and developing a productive momentum in bricklaying
speed and accuracy, came soon after the first level was laid.
- Brick Shape
Cupped, or "Banana" bricks plagued the project, particularly in the cream
brick. In retrospect, this probably could have been corrected by forcing the
manufacturer to improve production processes. In practice, however, the
very large order of bricks was made in one production run and the
programming constraints of the job made it difficult to stop progress to wait
for a better brick. Wherever possible, placement of artificial lighting was
amended to avoid glancing light being cast over the brickwork which would
have accentuated the effect of warped brick.
- Colour
Problems of brick colour batch variations were common in the cream brick,
but rare in the salmon brick. The quality control procedure adopted on site
was for the architect to sign samples of the lightest and darkest acceptable
brick colour of each type. Incoming brick pallets were then checked by the
Clerk of Works for compliance with the approved samples. Non-conforming
bricks were rejected for return to the manufacturer, or to be used in
below-ground or rendered applications. The greatest factor working against
detecting brick colour variations for bricks which got passed this process
was the method of finishing joints. As joints were bagged flush, considerable
amounts of mortar smear made it difficult to judge whether bricks were well
laid, whether they had chipped edges, or were likely to have colour batch
problems. By the time cleaning down occurred (i.e. following completion of
each wall to parapet height), it was too late to remove large areas of colour
mismatched bricks.
Fortunately, however, the blood-and-bandage pattern of banded colours
masked a lot of brick colour batch problems. Further, the subcontractor was
co-operative (because of the Clerk of Works eternal vigil!) and laid off
several brick pallets in each work area.
- Brick Joints
The joint design was to be struck flush. The bricklayers initially protested
against this, largely on the grounds that:
(a) The mix design was very lean, to achieve the lightest possible mortar
colour using off-white cement, and to avoid a true slip-joint between colour
bands. The lean mix was, in turn, slow to cure to a stiff enough consistency
to cut neatly with the trowel.
(b) Coarse sand (which was used in initial sample panels) resulted in the
trowel cutting action dragging out the mortar in an unsightly manner.
The problems were basically overcome by experimentation in methods of
"bagging" the finished joint. The solution was to change the sand to a finer
Sydney sand mix and to flush joints some 20 minutes (approximately 3
courses higher) after laying to allow the mortar to stiffen. Flushing was
achieved by a rag-covered sanding block.
The last (unresolved) difficulty was that perpends could never be flush struck
and bagged to a good line due to a slightly rounded arris on the bricks'
vertical edge.
- Scored Bricks
Given that three different types of face bricks were used, it was important to
avoid the additional cost of purpose-made sill bricks. Thus for both sill
bricks and half-brick batts, the manufacturer agreed to score the face during
extrusion of the green brick clay column. This enabled sills and half-bricks to
be bolster cut which is considerably cheaper than sawcutting. In retrospect,
purpose-made sill squints would have cost little more.
Conduit-bricks were produced as specials with voids to suit electric wiring
within double-face 110mm walls. This was not a success, as the
conduit-bricks were fired in their own batch, and invariably showed up as a
colour mismatch in the finished building.
- 110mm Double-Face Walls
For economy, a design decision was made to lay internal 110mm partition
walls to fair face each side. It quickly became evident that this was a
mistake, as the extruded bricks in use had a "first" and a "second" grade
face. The second face and markings originated in the conveyor rollers which
transport bricks through the extrusion, cutting and setting stages pre-kiln.
This was exacerbated by brick width tolerances, which in themselves mean
that the "second" face of a 110mm wall was out-of-plane, but combined with
multi-coloured bricks, the variation out-of-plane was even worse. One
should only attempt to design 110mm work double face if the brick face
appearance and width tolerances permit.
- Brick Impurity Control
The brick manufacturer's chosen method of controlling vanadium staining
(which was believed to be a problem relating to the particular clay being
used) was to silicon-dip all bricks just prior to palletisation. The vanadium
was certainly contained as a result (because its migration to the surface was
limited by the silicon "skin"), but the cure was worse than the complaint, as
the bricks were laid off wet and dry pallets, depending upon the weather at
the time of delivery. Locked-in moisture in some bricks, but not others was
very slow to dry out. The result was quite unsightly and appeared, to all
intents, like brick colour batch problems.
- Gauge
The design intent included creating a bold gauge (8 courses = 700mm) of
12mm bed joints, to keep polychromatic brick bands monolithic in
appearance. However, in practice, the fat bed joint in a relatively weak
mortar led to brickwork sagging if more than 20 courses were laid in a day.
This is not unusual in internal partition work, and slowed the job down.
- Internal Polychromatic Walls
The use of banded and panelled polychromatic brickwork on internal walls
worked well.
|
|
 |
CASE STUDY 2
GROUP HOUSING, DEPARTMENT OF HOUSING, GLEBE, SYDNEY
| Client |
N.S.W. Department of Housing |

Photo: Max Dupain |
| Architect | Philip Cox; Richardson, Taylor &
Partners Pty. Ltd. |
| Builder | Bona Builders Pty. Ltd. |
| Bricklayer | Fynjass Pty. Ltd. |
| Brick Supplier | Clark Brick Limited and State
Brickworks Pty. Ltd. |
| Contract Value | $12,500,000 |
| Brickwork Subcontract Value | $3,060,000 |
| Location | Glebe St, Glebe |
| | |
The project built in 1990, consists of 108 medium-density residential units for the
Department of Housing in an inner-city suburb. Construction is in loadbearing cavity
brickwork, rising 2 to 3 stories above reinforced concrete basement carparks.
Brick colours chiefly vary between adjoining units and architectural elements; the
design intent being to establish individual identity and liveliness of composition. Top
parapet coursing is invariably in darker brick for both visual strength and for better
weathering.
Relevant issues:
- Brick Selection
For a medium-density domestic project, the large volume of brickwork, and
the length of the site (one large inner-suburban block) led to difficulties in
contracting and quality control. For example, the loadbearing floor-slab
design coupled with the long narrow site, determined a slow overall program.
That program was at all times dependent upon the bricklaying subcontractor
who for a number of reasons, was a small firm. The combination of
small-scale subcontractors, program demands, inadequate supervision, and
the eruption of industrial unrest brought the project to a halt 60% through. At
that time the subcontractor went into liquidation. It is worth mentioning this in
the context of polychromatic brickwork - as the greater skill level and
supervision demands of polychromatic projects must confront the sometimes
volatile nature of bricklaying as an industry. It is not uncommon, as in this
case, that the technical challenges presented by polychromatic work, are
added to the strains of head contractors managing a team, firstly, driven by a
failing subcontractor, and then under daywork to complete the project.
There is merit in considering at tendering stage issues such as select
bricklaying subcontract lists, and dividing jobs into more manageable
contract sizes.
- Brick Order
At documentation stage, the architect contacted several major brickmakers
in an attempt to establish reliability of supply, colour uniformity, expansion
coefficients and the ability to stockpile a single-run production order. The
final selection of brick supplier was based largely on the preference for all
brick colurs (excluding cappings) to be from the one supplier and the right
colours when viewed in combination. The budget determined that only
extruded bricks would be used. Although the contractor was urged to place
a single production order, at the later stages of the job extra bricks were
supplied resulting in colour batch variation.
- Brick Colour Batch Problems
Over the life of the job, brick colour batch problems frustrated both architect
and builder, resulting in a loss of productivity, morale and smooth progress.
Colour variations were worse in creams than in deeper pinks. Despite signed
brick samples at the outset defining the acceptable colour and tonal range,
the manufacturer delivered brick colours outside these limits. In fairness to
the supplier, most colour problems were only identified when brickwork was
in place and cleaned. The practicalities of checking every incoming brick
pallet against signed samples were not achievable (although there remains no
better system). Further, the contractor's failure to order enough bricks
initially led to second and third production runs, in which the various clay
seam characteristics had altered. Much correspondence and interaction
between all parties concerned whether colour problems were short-term
(moisture differences between pallets as laid) or long term. More brick walls
were removed for relaying than solutions were forthcoming from the
contractual arguments over brick colour problems. The failure of the
bricklaying company made delineation of relative responsibilities difficult. The
design employed bricks of too similar a colour/tonal range. As a
consequence, colour batch problems in one brick type often blurred the
design distinction demanded between two adjacent brick panels.
At one stage within a single wall of cream bricks, the only acceptable means
of dealing with brick colour change was the introduction of a rendered
2-course band. This argues in favour of some polychromatic banding.
- Joint Design
A contributing factor to the lateness in brick colour problem detection was
the use of a flush struck joint. The amount of mortar smear on the brick face
(which would have been much less with a better bricklayer) was
considerable, making inspection difficult until the time of final clean.
- Brick Size Irregularities
"Banana" bricks and length variation of up to 8 mm, led to on-going difficulty
in maintaining flush joints and regular gauge.
- 'e' Factor Compatibility
One advantage of a single-sourced range of the main face bricks was that
coefficients of expansion were relatively close. This obviated slip joint
complications.
- Weathering
Although the red tile-faced bricks work well as a dirt-shedding parapet
brick, the cream brick areas suffer from dark mortar joints as weathering
(dirt runoff and fungal growth) occurs. In the context of polychromatic work,
where light brick panels attract more visual scrutiny, greater care in
weathering the finished brickwork is needed.
|
|
 |
CASE STUDY 3
OFFICE BUILDING, CASTLE HILL
| Client | Amway of Australia |

Photo: David Moore |
| Architect | Philip Cox; Richardson, Taylor &
Partners Pty. Ltd. |
| Builder | Civil & Civic Pty. Ltd. |
| Bricklayer | Nolan Constructions Pty. Ltd. |
| Brick Supplier | Zacuba Red Wirecut and Bathurst
Hartley Cream |
| Contract Value | $7,000,000 |
| Brickwork Subcontract Value | $160,000 |
This is a 2,200m2 office building in an industrial park setting built in 1991. Two
storey in scale, the construction is an outer brick cladding skin wwith steel wall
stiffeners fixed to a reinforced concrete frame. Internal walling throughout is
lightweight. Face brickwork is banded with a very simple dark brick plinth and
some panels of the same brick surrounding major windows and entries.
Relevant issues:
- Brick Selection
The initial design intent was to select a light cream with a medium salmon
brick at the plinth. Every available dry-pressed and extruded cream brick
was surveyed. Two problems, endemic to New South Wales creams,
recurred. Firstly, the majority of creams are pasty, parchment and
buff-coloured, lacking freshness and vigour. A second group, including the
dry-pressed creams, consists of many overly yellow creams. Yellow can
easily dominate en masse, making a cream/salmon combination difficult. The
solution was to change focus to a flesh/cream which avoided the dullness of
buff-creams and the danger of yellow domination. The flesh/cream works
well with a range of salmon and deep pinks. The red (salmon) brick finally
selected had to be strong to contrast with the flesh/cream. The first red brick
nominated was chosen on the basis of several sample packs delivered by the
manufacturer. When the first pallet arrived on site, a combination of marble
frit on the brick face (removable, but not easily) and colour variations
suggesting an oxide additive made the brick unacceptable. An alternative red
brick was quickly found.
- Brick Gauge
The design anticipated brick length variations between cream and red bricks.
A two-course cut soldier broke gauge between colour bands. On site, the
cream and red face bricks as first delivered were measured and were of
average length:
Cream - 229mm
Red - 224mm
Detailed discussions between architect, contractor and bricklayer were held.
In this case the builder took a stand that the brick supplier could do better.
This was rewarded by the brick supplier then delivering red bricks of an
acceptable average length of 227mm. Although in the final analysis the
two-course soldier was deleted, the perpend gauge variation between red
and cream bricks was acceptable. The general problem that simple colour
banding raises is this difference in brick size and the difficulty in both keeping
perpends vertically aligned and maintaining a similar perpend dimension.
- Colour Batching
Colour variations in the cream brick, whether by different moisture levels of
brick or by brick batch differences, were problematic in the latter stages of
the project. The chief problem is the lateness at which such colour variations
come to light.
- Joint Design
A client preference for mortar colour matching the cream brick led to the use
of a strong coloured sand (in the bush sand component of the mix). In turn,
the mortar sand grain size was coarser than normal - inconsequential with
raked joints, but more difficult with flush struck joints as was the case here.
Cutting a coarse sand mortar to a clean and full joint is harder, and any brick
joint voids in the initial bricklaying work are difficult to fill or rectify after the
mortar has set.
|
|
 |
CASE STUDY 4
OFFICE BUILDING, SURRY HILLS
| Client | Joint Venture between Allen Jack +
Cottier Partnership Pty. Ltd. and
Commercial and Domestic Finance Pty.
Ltd. |
|
| Architect | Allen Jack + Cottier Architects |
| Builder | Reed Constructions Pty. Ltd. |
| Bricklayer | Two unknown subcontractors |
| Brick Supplier | Clark Brick Limited and Bowral
Brickworks Pty. Ltd. |
| Contract Value | $2,500,000 |
| Brickwork Subcontract Value | $150,000 |
This is a 5 storey office building in an inner-city suburb built in 1988. Construction
is an outer brick cladding skin fixed to a concrete frame. Internal walling is
lightweight gypsum plaster blockwork. The design intent was to create a
commercial building compatible with a streetscape of terrace houses, large
warehouses and a church; all of loadbearing brick construction. Face brickwork is
banded in varying widths, colours and textures.
Relevant issues:
- Brick Selection
Several factors dictated the colour and shape of the bricks. The initial design
intent was for a building banded from a textured, dark coloured base to a
smooth, lighter top. The lower section (from a varying ground line to Level 3)
is generally carparking with few windows but the need for large free area
ventilation openings. To achieve a solid base, many small ventilation openings
were incorporated into two dark coloured alternating bands. Texture in the
base was achieved by using squint bricks laid with points out in stack bond
alternating with ventilation openings. The upper section is banded with three
colours, one of which also occurs in the base. Altogether four colours are
used with one colour requiring a squint brick as well as a standard brick
shape.
In consideration of the above factors the initial preference was for all bricks
to be supplied by one manufacturer. In the end this was not possible with
three colours (red, pink and cream) from one manufacturer and the other
colour (dark brown) from a different supplier. All bricks are dry pressed.
- Brick Size
Brick sizes varied greatly between the four colours with average stretcher
lengths as follows:
Brown 225mm
Cream 232mm
Pink 232mm
Red 228mm
As a consequence, the initial dimensional setout was abandoned in favour of
a setout of "best fit". This resulted in some unsightly fat perpends in the short
lengths of walling in the red bands to maintain horizontal gauge with the
cream and pink bands.
The 3mm difference in length between the brown and red bricks was not
discernible in the alternating bands of Flemish bond red brickwork with
bands of brown squints laid in stack bond. This "textured" base was
separated from the upper brickwork by an exposed concrete slab toe.
- Bricklaying
The textured base, while not particularly complicated, was slow to lay and
the narrow bands resulted in the need to frequently supply different bricks
(colour and shape) to the scaffolds. Some care was required to ensure the
headers laid in the red band lined up with the header width ventilation
opening in the stack bond brown band. The bricklayers would only do this
work on an hourly rate basis and a small team was used to ensure
consistency for the whole base. Overall this base was very costly in time and
money to the builder.
In an attempt to minimise his losses on the brickwork subcontract, the
builder used a different bricklaying subcontractor after the Level 3 concrete
toe. This very large team proved difficult to control and, combined with the
brick size problem, resulted in much brickwork being demolished and rebuilt
before it was accepted by the architect.
|
|
 |
CASE STUDY 5
CAROLINE CHISHOLM HIGH SCHOOL, CHISHOLM, A.C.T.
| Client | National Capital Development
Commission (now ACT Public Works) |
 |
| Architect | Lawrence Nield & Partners Australia Pty.
Ltd. |
| Builder | Civil & Civic Pty. Ltd. |
| Bricklayer | Gougard (original contractor) |
| Brick Suppliers | Clifton Bricks
Extruded 'run-of-kiln' red
Cowra Brickworks
Dry-pressed red
Dry-pressed silver
Bowral Brickworks
Simmental silver
Goulburn Brickworks
Dry-pressed red |
| Contract Value | $7,300,000 |
| Brickwork Subcontract Value | Not known |
| | |
Caroline Chisholm High School, ACT
Architect: Lawrence Nield and Partners |
The high school consists of twelve separate buildings, of single storey loadbearing
cavity wall construction and diaphragm wall construction to the Gymnasium Hall.
The external brickwork is banded red and silver, three courses each to twelve
courses, then 'run-of-kiln' red above. Lintels are in the dry-pressed red constructed
as a flat arch. A toothed course runs for the perimeter of each building at eaves
level, topped by a brick-on-edge. Parapet coursing was documented as solids
'run-of-kiln' red.
Because of the scale of the Gymnasium, the base course of red and silver
dry-pressed bricks was increased in height with additional banding at the eaves and
to the gable ends.
In Stage 3 the bricklayer fell behind the construction programme, delaying the
erection of steel roof framing. Where previously the steel was supported by the
brickwork, 'carport' columns now supported the main roof frames, encased by
brickwork and the brick cavity grout filled.
Construction started in October 1983, Stage 1 was completed in January 1985,
Stage 2 in May 1985 and Stage 3 in December 1985.
Relevant issues:
Project Size
The 7200m2 building required 920,000 bricks. The project was constructed in
three stages to allow a staged occupation because of the local boom in residential
development. The 9 hectare site allowed large quantities of bricks to be stored on
site. Whilst Clifton Bricks quick turnover resulted in large quantities of rejected face
brick, Cowra Brickworks was not able to supply at the required rate. Cowra
Brickworks eventually fell behind programme in the production of dry-pressed
silver bricks and Bowral supplied the alternative - Simmental Silver. When Cowra
Brickworks could not supply the red bullnose for door sills, Goulburn Brickworks
fortunately had a similar brick.
'e' Factor
The base course bricks were all dry-pressed, obtained from similar clay material
and fired by the same process. The 'e' factors were, however, different (0.6mm/m
red; 0.282mm/m silver). The 'run-of-kiln' red surprisingly had a low 'e' factor (0.25
mm/m). Advice on brick growth was provided by the BDRI and a relatively weak
mortar mix (1:1:6) was specified removing the need for a slip joint between the
brick bands.
Brick Size
The different clay material and manufacturing process resulted in the 'run-of-kiln'
red bricks being some 4-5mm shorter than the dry-pressed bricks. To maintain the
horizontal brick rod it was necessary to increase and/or reduce the perpends. The
articulation of external brick skin at the windows (30mm indent for window)
required the bricklayer to accurately set out the width of the horizontal dimensions
at the footing level.
Brick Quality
Fissures and cracks to the face of the 'run-of-kiln' red bricks plagued the project.
The elimination of rejected bricks was important because of the incidence of
freezing temperatures where water trapped in the crack would freeze and cause
spalling to the outside face. Constant supervision resulted in reject bricks being cut
out of facework. By the end of Stage 1 the bricklayers were more selective when
choosing facebricks.
Brick Colour
Problems in brick colour variations were overcome by screening the pallets as they
arrived on site and mixing pallets when selecting bricks. Non-conforming facebricks
were returned or used in common work.
Brick Joints
Brick joints were ironed with a 10mm raked joint between the brick colours. The
raked joint accentuated the banding and concealed any movement at the bed joint
between differing bricks.
Special Bricks
Sill bricks were to be manufactured as a 'cant' brick. Window sills were laid
brick-on-edge with a 5mm fall; door sills were laid with a bullnose brick in a
Goulburn red, similar to the Cowra red.
Parapet copings were specified to be a 'run-of-kiln' red solid. At the time of
detailing the parapets BDRI recommended the use of solids to increase the
impermeability of the top courses and increase the mass. Clifton Bricks produced a
solid in the same colour, however, when the pallets arrived on site they were a
peach colour. Several firings later, the colour approached the red of the extruded
bricks. The increase in the mass of the brick and additional water content were
given as the reasons for the colour difference.
Internal Polychromatic Walls
Corridor walls were laid as face, red to twelve courses (dado height to disguise the
grubby marks and bag scrapes) with silver above. Walls were laid as face one side
only, the other rendered and painted. Particular care was required when chasing for
services. Steel 'T' wall stiffeners were co-ordinated with the brickwork to work
with the horizontal brick rods.
Quality Control
The original bricklayer left the project at the end of Stage 2 (50% of the bricklaying
contract). At the time the residential market was booming and bricklayers were
being paid more per thousand for simple residential than the rate tendered on the
high school. The contract was terminated and a new 'gang' was engaged to
complete the works. This involved a review of quality standards in both brick
selection and laying techniques with the new bricklayers.
'Chisholm' Lintel
For openings wider than could be accommodated by a galvanised steel arch bar or
angle a 'Chisholm' Lintel was designed. Proprietary alternatives were investigated,
e.g. Hesbia lintel, but were rejected for two reasons:
(a) The galvanised strip built into the bed course must be tensioned and there is no
guarantee it will not corrode.
(b) Stretcher Bond Straight brick coursing spanning a three metre opening with no
visual 'architectural' device is not convincing.
The 'Chisholm' lintel consists of a reinforced concrete beam formed in a wide brick
cavity with the bricks propped and used as permanent formwork. Brick ties are
built into all the vertical and horizontal joints.
The flat arch used for all window and door openings was again expressed in the
brickwork for the larger openings. This detail was also employed in the 760mm
diaphragm walls of the Gymnasium where an expressed concrete lintel was not
appropriate.
|
|